Week 59, Day 5

Week 59, Day 5:

  • Quite a busy day finishing off various jobs on the inside and some of the landscaping on the outside
  • Patching up the plasterboard removed to apply the air tightness tape
  • Tiling the floor in the Utility Room
  • Filling the planting beds which are part of the Retaining Wall on the north side with topsoil
Week 59, Day 5

Week 59, Day 5

Rubber floor tiles in Utility Room

Rubber floor tiles in Utility Room

Topsoil in planting beds on north side

Topsoil in planting beds on north side

Week 58, Day 5

Week 58, Day 5:

  • More progress on the ground works, back-filling behind the retaining wall and in the planters and levelling out the area by the side entrance
    • The lower section of retaining wall will be planted with ground-cover plants, and so it needs filling with topsoil and not the MOT 1 stone which can be seen in the photo, which will have to be dug out and replaced
    • This wall also needs lowering by one course of blocks so it lines up correctly with the middle step
  • A little more work on the outdoor electrics, setting galvanized steel conduit boxes into the blockwork and wiring the SWA cable into those for the outside lights and sockets
    • Most of the cables will be covered by the stone cladding
Week 58, Day 5

Week 58, Day 5

Back-filled retaining wall

Back-filled retaining wall

Levelled area by side door

Levelled area by side door

Cable boxes for outdoor lights and power sockets

Cable boxes for outdoor lights and power sockets