Week 37, Day 4

Week 37, Day 4:

  • More work on the electrical first-fix
  • More work on the plastering, mainly the ceiling in the Open Plan kitchen and family room
Week 37, Day 4

Week 37, Day 4

Services cupboard in the kitchen ready for plastering

Services cupboard in the kitchen ready for plastering

Plasterboard on most of the ceiling in the open plan area

Plasterboard on most of the ceiling in the open plan area

That square white plate is the extract vent for the kitchen, which takes a replaceable grease filter (inside the recess) behind a cover grid.

Week 37, Day 3

Week 37, Day 3:

  • More plastering
  • More electrical and plumbing first-fix, including a lot of work in the Plant Room
  • Forming the dropped-ceiling in the ground floor shower room
Week 37, Day 3

Week 37, Day 3

DHW tank (left) and GSHP unit (right) installed in the Plant Room

DHW tank (left) and GSHP unit (right) installed in the Plant Room

Acoustic rubber pad under GSHP

Acoustic rubber pad under GSHP

Framework for dropped-ceiling in ground floor shower room

Framework for dropped-ceiling in ground floor shower room