Week 59, Day 3 Posted on 2016-11-30 by dMb Reply Week 59, Day 3: Mostly working on the main air leak found last week – or at least what is hopefully the main air leak – above the En-Suite to the Master Bedroom, adjacent to the Balcony Week 59, Day 3 Remedial air tight taping in the Master Bedroom En-Suite
Week 59, Day 2 Posted on 2016-11-29 by dMb Reply Week 59, Day 2: No building work on site today Week 59, Day 2