Week 46, Day 2

Week 46, Day 2:

  • Laying the new telephone cable to the underground joint box to the north-west of the house
  • Clearing the area to the east of the house, locating the water supply pipe and digging trenches for the foul drainage connection to the Biorock treatment system
Week 46, Day 2

Week 46, Day 2

Digging the drainage trenches

Digging the drainage trenches