Week 53, Day 4

Week 53, Day 4:

  • Nearing completion on the second-fix plumbing, with all the heating systems now operational and good progress on the remaining sinks and taps
  • As the build nears completion the focus is switching more to cleaning and tidying rooms once all the work in them has been completed
Week 53, Day 4

Week 53, Day 4

Vanity top and sink installed in First Floor bathroom

Vanity top and sink installed in First Floor bathroom