Week 81, Day 5

Week 81, Day 5:

  • The team from Full Metal Roofing were back again to finish up the last of the zinc cladding around the windows
  • With the exception of a very few minor items this marks the completion of the full scope of work contracted to Burton Building Solutions
    • The remainder of the landscaping and the stone cladding on the walls at the front of the house were always excluded from that scope of work
Week 81, Day 5

Week 81, Day 5

Completed zinc cladding outside the Dining Room window

CC BY-SA 4.0 Week 81, Day 5 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.