Week 73, Day 4

Week 73, Day 4:

  • The build team are back on site so I’m going to re-start the daily Blog updates and call this Week 73
  • There’s not much to see from the overview shot but they’re proceeding with the rainwater drainage as shown in the second photo below
  • The other big event of the day was the switch-on of the Solar PV installation – with the EPC in-place – all very uneventful since it “just worked” and managed to generate 15 kWh on a fairly overcast day
    • The SolarEdge inverter is logging data to the SolarEdge Internet portal so I’ve got some work to do to extract performance data from there via their API
Week 78, Day 3

Week 73, Day 4

Trench for rainwater drainage at south side

CC BY-SA 4.0 Week 73, Day 4 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.