Week 77, Day 3

  • More ‘finishing’ jobs outside and snagging inside
  • Sealing the joints between the concrete linear drainage units and installing the galvanised steel gratings on those (see photo)
  • Replacing one of the stainless-steel handrail tubes on the balcony which had started to corrode (must have been the wrong specification of stainless steel)
Week 77, Day 3

Week 77, Day 3

Galvanised steel gratings over linear drain at north side of house