Outbuildings: 2026-01-22 Update

Outbuildings: 2026-01-22

While almost all of the building work was completed before the end of 2025, there were a few items outstanding which have been attended to over the past couple of days:

  • The rainwater drainage inspection chamber in the North-East corner of the Courtyard (top-left of the overview photo) has always been holding 30-40mm of water – implying an inadequate ‘fall’ on the outlet pipework.
    • The fall was checked with a laser level on Tuesday, which confirmed the chamber was set at the right level and pointed to some sort of issue on the downstream pipe run.
    • Excavation of that pipe run showed there was a ‘hump’ in the pipe which was causing the issue – partially due to it passing over a separate underground pipe connected to an Aco doorway drain.
    • With the pipe run re-routed away from the other pipe and re-levelled at the correct fall, the rain is now draining out of the inspection chamber.
  • The ground in the Courtyard has always been prone to holding pools of standing water – which was evident before construction started. As a consequence, a network of ‘land drain’ pipework was installed, formed from four ‘legs’ running east-West (which will end up in the middle of future planting beds).
    • The expectation was that there would at least be no standing water in the immediate vicinity of those land drains – but that wasn’t the case, and in fact there were some pools of water directly above the drains.
    • The issue turned out to be the use of solid clay as the back-fill material over the land drain pipes – and in some cases inadequate pea gravel over those pipes.
    • The agreement with the build team was that they would remove the layer of clay overlaying the land drains and top-up the pea gravel cover over the pipes to the specified 100mm depth – and then I will fill the trenches with some more free-draining soil from elsewhere on the site, as part of the work required to prepare the soil between the drains for planting.
  • Some other finishing touches that happened to be scheduled for today were for the windows and doors.
    • One of the window handles was from a faulty batch, and the lock cylinder kept falling out – so that handle was replaced (from a new, good batch).
    • There was some install-time damage to one of the door handles, which was also replaced.
    • The original window sills turned out to be too ‘deep’ to fit properly so those were re-made and fitted today.
    • A minor manufacturing defect on the bi-fold door meant the bottom seal had been torn – and would be torn again if one of the hinge fixings wasn’t adjusted, so that hinge was re-fitted and the seal replaced.

Outbuildings: Week 40, Day 3

Outbuildings: Week 40, Day 3

Quite a busy day on-site, with the most visible progress being the installation of the galvanised steel handrail and balustrade for the external staircase.

Galvanised steel handrail and balustrade for the external staircase

This will be left with its galvanised finish rather than being painted, to match the galvanised frames for the adjacent door and window and the galvanised light fittings – and the zinc roof of the house. The bright silver finish will darken down a bit over time.

The main build team were also back to work through the initial snagging list from the Architect. Most of that got completed, though the testing of the foul drainage showed up a major leak in an underground pipe which is presumed to have been fractured by the weight of a digger driving over it; there’s not much depth of soil ‘cover’ over the underground pipes in the Courtyard. The damaged section of pipe was replaced but the nature of the damage means there might be further damaged sections.