Week 66, Day 3

Week 66, Day 3:

  • Replacing the sound insulation and the plasterboard at the western end of the Open Plan room
  • Progressing with the first-fix wiring for the outdoor lights and sockets
Week 66, Day 3

Week 66, Day 3

Replaced plasterboard at western end of Open Plan room

Week 57, Day 5

Week 57, Day 5:

  • Installing the armoured cables for the outside lights and sockets
    • To reduce the number of holes through the air tight barrier these exit the house in one location then loop around the outside
  • Installing more of the oak cappings for the glass balustrades around the staircase
Week 57, Day 5

Week 57, Day 5

Armoured cable for outside lights

Armoured cable for outside lights

Oak capping for glass balustrade fixings on first-floor landing

Oak capping for glass balustrade fixings on first-floor landing