Week 46, Day 3

Week 46, Day 3:

  • Installing the inspection chambers (bedded in concrete) and the drainage pipes (bedded in pea shingle) to the east of the house
  • More second-fix plumbing, installing the wall-mounted WC in the Master Bedroom En-Suite and fitting some more shower riser bars and spray heads
Week 46, Day 3

Week 46, Day 3

Main run of foul water drainage; Biorock treatment tank in the distance

Main run of foul water drainage; Biorock treatment tank in the distance

Wall-mounted WC in Master Bedroom En-Suite

Wall-mounted WC in Master Bedroom En-Suite

Week 46, Day 2

Week 46, Day 2:

  • Laying the new telephone cable to the underground joint box to the north-west of the house
  • Clearing the area to the east of the house, locating the water supply pipe and digging trenches for the foul drainage connection to the Biorock treatment system
Week 46, Day 2

Week 46, Day 2

Digging the drainage trenches

Digging the drainage trenches