Week 41, Day 3

Week 41, Day 3:

  • I’ve probably not done the continued good progress on the plastering justice in recent posts so there’s a photo of the Living Room nearing completion
  • The ceiling of the balcony has been insulated, including the steel beams
  • The kitchen is progressing, with all the drawers now installed
  • More second-fix electrical and plumbing
Week 41, Day 3

Week 41, Day 3

Plastering in the Living Room

Plastering in the Living Room

Insulation over balcony

Insulation over balcony

Kitchen units almost ready for appliances

Kitchen units almost ready for appliances

Week 30, Day 2

Week 30, Day 2:

  • The first really wet day in several weeks
  • More first-fix, electrical and plumbing
  • Insulation and air-tight taping around the steelwork in the southern bedrooms
Week 30, Day 2

Week 30, Day 2

Insulating the steel beam in the second bedroom

Insulating the steel beam in the second bedroom

The pro clima Contega PV tape will get plastered into place to form an air-tight barrier.