Outbuildings: Week 5, Day 3

Outbuildings: Week 5, Day 3

All the below-DPC walls are now completed and all the crushed stone has been spread inside the buildings. The recycled stone has also been spread on the outside of the buildings, as a base for the scaffolding and to make for better working conditions in wet weather.

The floor insulation has been delivered but will not be installed just yet; the floor slab concrete is scheduled to be poured one week today (Wednesday 16th April) and there’s not much more preparation required for that so work will now pause until Monday.

Outbuildings: Week 5, Day 2

Outbuildings: Week 5, Day 2

Another two lorry-loads of crushed stone delivered; one for inside the buildings, under the insulation, and another one (recycled crushed hardcore) for the working area around the buildings.

With most of the stone spread out inside the buildings, using the digger, the access routes for the digger left in the below-DPC brickwork were (mostly) filled in, to be completed tomorrow.