Week 36, Day 1

Week 36, Day 1:

  • A site meeting with the Architect to agree the revised specification for the Zinc Roof and its Structured Underlay
    • This is now agreed but Full Metal Roofing need to finish another large project first so they won’t be starting work for a couple of weeks
  • More progress on the plastering, finishing off the walls in the Office and other areas on the Second Floor
  • More progress on the Plant Room pipework
  • The tele-handler was off-hired
Week 36, Day 1

Week 36, Day 1

Plaster skim coat complete on the walls in the Office

Plaster skim coat complete on the walls in the Office

Alcove in the Second Floor Bathroom

Alcove in the Second Floor Bathroom

Concealed cistern in the Master Bedroom En-Suite

Concealed cistern in the Master Bedroom En-Suite