Week 36, Day 1:
- A site meeting with the Architect to agree the revised specification for the Zinc Roof and its Structured Underlay
- This is now agreed but Full Metal Roofing need to finish another large project first so they won’t be starting work for a couple of weeks
- More progress on the plastering, finishing off the walls in the Office and other areas on the Second Floor
- More progress on the Plant Room pipework
- The tele-handler was off-hired
![Week 36, Day 1](http://www.marshflattsfarm.org.uk/wordpress/wp-content/uploads/2016/06/20160620T1500Z.jpg)
Week 36, Day 1
![Plaster skim coat complete on the walls in the Office](http://www.marshflattsfarm.org.uk/wordpress/wp-content/uploads/2016/06/IMG_2308.jpg)
Plaster skim coat complete on the walls in the Office
![Alcove in the Second Floor Bathroom](http://www.marshflattsfarm.org.uk/wordpress/wp-content/uploads/2016/06/IMG_2300.jpg)
Alcove in the Second Floor Bathroom
![Concealed cistern in the Master Bedroom En-Suite](http://www.marshflattsfarm.org.uk/wordpress/wp-content/uploads/2016/06/IMG_2324.jpg)
Concealed cistern in the Master Bedroom En-Suite