Week 36, Day 1:
- A site meeting with the Architect to agree the revised specification for the Zinc Roof and its Structured Underlay
- This is now agreed but Full Metal Roofing need to finish another large project first so they won’t be starting work for a couple of weeks
- More progress on the plastering, finishing off the walls in the Office and other areas on the Second Floor
- More progress on the Plant Room pipework
- The tele-handler was off-hired
Week 36, Day 1
Plaster skim coat complete on the walls in the Office
Alcove in the Second Floor Bathroom
Concealed cistern in the Master Bedroom En-Suite