Outbuildings: Week 39, Day 1

Outbuildings: Week 39, Day 1

Good progress on the plumbing today, with the pipework now completed in the Ground Floor Store Room which is the ‘hub’ for the plumbing installation – though it still needs insulating (especially since the store room will remain unheated). With this pipework completed, there is now mains water coming into the Outbuildings (via the blue MDPE pipe in the photo below) and harvested rainwater in both the Outbuildings and the House (coming in from the submersible pump in the underground tank via the flexible hose connection into the black and yellow pump controller, and going out to the House via the black and green MDPE pipe, running into the same duct as the blue pipe).

Mains and Rainwater pipework in the Ground Floor Store Room

The diagram pinned to the wall is a schematic I drew for the plumbers, showing how the components needed to be arranged – reproduced below.

Schematic for rainwater harvesting pipework

I’ll write more about the rainwater harvesting system in a separate technical article, since it’s a relatively unusual thing to incorporate in a domestic property and I’m pleased with how it’s all come together. The Wisy Multimat pump and controller (in the photo with a temporary plastic bag rather than the supplied cover) are impressively very well-engineered. While they weren’t cheap they seem good value. The pump and controller are both critical components of the rainwater supply system and it’s not at all easy to arrange for a mains water backup if one of them fails, due to the regulations about protecting mains water supplies from contamination from “Category 5” liquids (since rainwater is considered as ‘bad’ as raw sewage).

Outbuildings: Week 37, Day 4

Outbuildings: Week 37, Day 4

The floor covering team were back on-site, since they’re happy the self-levelling screed they laid on Monday has dried out enough for further work to proceed. They spent the day tidying up a few areas that weren’t as smooth as they’d like and fitted the ‘coved’ skirting and the capping strip that will cover the top of the vinyl. The weather has turned cold so it’s needing some heating in the Utility Room to make the flooring sheet pliable enough to lay and form up at the edges – ideally it wants to be 18C.

The plumber was back on site too, with the priority for them being the underground mains connections into the new building and removing some redundant underground pipe loops dating back to the House build. While those had been isolated via underground stop taps, it seemed unwise to trust those long-term, so the tee fittings were replaced with straight couplers. There’s just one more loop to remove tomorrow, once the hole dries out a bit more. Then two deep holes that have been open for a few weeks can be filled in.

There was also more progress on the GrassGuard perimeter to the block-paved parking area, which is starting to look much closer to being finished.

Ongoing progress on the Marshalls GrassGuard perimeter around the block-paved area

A larger digger and a dumper truck were also delivered in preparation for the arrival of the replacement concrete headwall, which is due tomorrow.