Outbuildings: Week 39, Day 1

Outbuildings: Week 39, Day 1

Good progress on the plumbing today, with the pipework now completed in the Ground Floor Store Room which is the ‘hub’ for the plumbing installation – though it still needs insulating (especially since the store room will remain unheated). With this pipework completed, there is now mains water coming into the Outbuildings (via the blue MDPE pipe in the photo below) and harvested rainwater in both the Outbuildings and the House (coming in from the submersible pump in the underground tank via the flexible hose connection into the black and yellow pump controller, and going out to the House via the black and green MDPE pipe, running into the same duct as the blue pipe).

Mains and Rainwater pipework in the Ground Floor Store Room

The diagram pinned to the wall is a schematic I drew for the plumbers, showing how the components needed to be arranged – reproduced below.

Schematic for rainwater harvesting pipework

I’ll write more about the rainwater harvesting system in a separate technical article, since it’s a relatively unusual thing to incorporate in a domestic property and I’m pleased with how it’s all come together. The Wisy Multimat pump and controller (in the photo with a temporary plastic bag rather than the supplied cover) are impressively very well-engineered. While they weren’t cheap they seem good value. The pump and controller are both critical components of the rainwater supply system and it’s not at all easy to arrange for a mains water backup if one of them fails, due to the regulations about protecting mains water supplies from contamination from “Category 5” liquids (since rainwater is considered as ‘bad’ as raw sewage).

Outbuildings: Week 38, Day 2

Outbuildings: Week 38, Day 2

The long-awaited concrete headwall was finally delivered and quickly installed and connected up to the flow-control chamber ‘downstream’.

Concrete headwall installed at the West end of the stormwater attenuation pond

With the outfall from the pond taken care of, work can proceed to level off the base of the pond before moving on to install the inlet – though there will need to be a bit of tidying-up of the pond walls around the headwall at some point.

The small load of ready-mixed concrete that had been ordered to reinforce the foul drainage pipe under the access road to the block-paved parking area arrived as scheduled. Once that has set the stone foundation for that access road can be installed, making the parking area and the garages accessible.

Foul drainage pipe between the House and the Biorock sewage treatment plant encased in concrete

I also completed a bit more preparation of the rainwater harvesting system by installing the submersible pump in the underground tank and routing its electrical cables and delivery hose to the pump controller in the adjacent building. A quick test of the pump, to flush through the delivery hose before connecting that to the inlet on the controller, showed it is working well. At their next visit, the plumbers should be able to get the rainwater supply working within the Outbuildings – since they’ve already fitted the meter, the expansion vessel and most of the other components required to enable that.