Week 59, Day 4

Week 59, Day 4:

  • More progress on some “finishing” jobs – for example the oak trim around the staircase and the porcelain tiles by the front door
Week 59, Day 4

Week 59, Day 4

Porcelain floor tiles by Front Door

Porcelain floor tiles by Front Door

Oak trim around stair balustrade

Oak trim around stair balustrade

Week 58, Day 1

Week 58, Day 1:

  • Very heavy rain all day, hence the rain spots on the camera lens and the lights on inside at 3pm – and a mini lake on the driveway
  • Good progress with various of the internal snagging items and the installation of the remaining stair end-caps and the last of the oak for the glass balustrades
Week 58, Day 1

Week 58, Day 1

Last section of oak covering the fixings on the glass balustrades

Last section of oak covering the fixings on the glass balustrades

Completed end caps on the ground-to-first floor staircase

Completed end caps on the ground-to-first floor staircase