Outbuildings: Week 16, Day 5

Outbuildings: Week 16, Day 5

There are ‘valleys’ where the east-west roof over the Utility room (on the right of the photo) meets the north-south roof over the Workshop (across the back of the photo), where the height of the roof trusses needs to reduce and additional support is required for the valley tiles.

Further progress on the west-facing gable wall on the end of the Garage block, shown in the photo below. The first-floor doorway is intentionally off-centre to try to allow enough room for the external staircase.

Work proceeding on the brick (and block) gable wall, incorporating the door into the ‘Hay Loft’ room