Outbuildings: Week 36, Day 5

Outbuildings: Week 36, Day 5

Very wet and windy all day thanks to Storm Claudia. The block paving work planned to start today got rained off and will now start on Saturday. The 6mm stone required as underlay for the permeable paving was delivered – along with the Marshalls GrassGuard blocks (which had been expected a week ago) – so everything is now ready for the block paving to start in the morning, as long as the weather is sufficiently improved.

The garage door roller shutter that had been failing to respond was brought back to life with a full reset by the installers – though while it was stuck open it allowed a fair bit of rain into the garage (which tends to pool away from the doorway thanks to a slight slope in the floor slab). Some rain came under the other roller shutters too – I think some sort of retrofit threshold strip will be required to keep the water out, since the roller shutters already do a decent job of pressing down their rubber sealing edge.

Almost all of the alarm system set-up is now complete – apart from the commissioning of the radio link back to the house, which is waiting on some more components.

Outbuildings: Week 36, Day 2

Outbuildings: Week 36, Day 2

The garage door installation team were back on site to finish up the last few bits and pieces, which only took a couple of hours. The Hormann RollMatic 2 shutters have quite a sophisticated motor control system, with a ‘soft stop’ at the bottom of their run and they lift faster than they lower (when they need to be checking for an increase in motor load that might indicate an obstruction). The four-button remote controls have been configured to operate all of the doors from each remote control.

The electrical installation team were also back on site, completing all the outdoor lighting, the last of the indoor lighting, the special sockets for the rainwater harvesting system and some of the work on the two myenergi Zappi electric car chargers. A few more hours tomorrow should see the electrical installation completed – apart from the electric shower, which needs to wait until the wall has been tiled (which needs to wait for the floor covering to go down).

Completed Garage Doors with their External Lighting

One other bit of progress was a trial fitting of the steel handrail for the external staircase, before that gets fully welded and galvanised. It just needs a couple of adjustments to the fixing brackets – and the ‘return’ section of the rail for the landing needs fabricating.

Trial fitting of the steel handrail for the External Staircase