Myenergi Zappi EV Charge Point First Test

Now the parking area is accessible to cars and with it being forecast sunny for most of the day, it seemed a good opportunity to put the electric car in the garage for the first time and test out charging it with the Myenergi Zappi EV charge point, using excess solar generation that probably wouldn’t fit in the PowerWall battery and would hence be curtailed.

BMW i3 EV in the Garage, connected to one of the two Myenergi Zappi EV Charge Points

The BMW i3 looks a bit lost when viewed from the CCTV camera that monitors the garage. The plan was always to park that car there, which influenced the location of the ‘primary’ Zappi EV charge point at the back of the Garage, between the first and second parking bays. (The ‘secondary’ Zappi is just visible at the bottom-right of the photo, where it can be used from the third parking bay and for cars parked outside.)

One of the key features of the Zappi unit is that it can harvest excess solar generation and charge a car at a variable rate to make best use of the solar generation that would otherwise be exported (or curtailed – depending on the configuration settings). While it’s useful to have this capability, with both a house battery and a decent export tariff it will typically be more economical to charge the car on the off-peak overnight rate and get paid to export solar generation during the daytime – except when there’s more solar power than can be exported or used to charge the house battery1.

With the PowerWall having a DC-connected battery integrated with the solar PV inverter, it’s not possible for the Zappi to tell whether power coming from the PowerWall (which it monitors using a CT clamp) is originating from the solar panels or from discharging the battery. It has a second CT clamp on the main grid connection, so it does know whether the site is Exporting or Importing overall – but the Zappi manual admits to the limitations in such circumstances.

With the Intelligent Octopus Go tariff, Octopus get to control when the car charges – and will either do this in the normal overnight off-peak period or they will add an ‘extra’ off-peak period if they decide to charge the car at other times. Before having the Zappi it was necessary to have Octopus control the car via the BMW API but now it is preferable to have them control the charger instead2. Right now – even when deleting and re-adding the Electric Car ‘device’ and when telling them there is a Zappi charger, they still want to control the car. I’ve submitted an online form which is meant to ask them to control the charger instead – for which they’ll ask for the Myenergi account details, not the BMW account details. The form said to allow up to one working day for that to take effect, so I’ll try re-adding the ‘device’ in a day or so.

The other configuration setting that needs attention before allowing Octopus free rein over overnight EV charging is the “Import Limit” for the PowerWall 3. Right now there’s no import limit set so there’s a risk of:

  • Octopus charging the electric car at 7.5 kW
  • Tesla charging the PowerWall battery at 8 kW
  • The House drawing 3.5 kW or more if both heat pumps are running

That would make a total of 19 kW or 82.6 A at 230V, which is more than the rated capacity of the DNO fuse on the grid connection and it would be A Bad Thing to have that fuse blow3. Given that the PowerWall is enforcing the grid export limit we might as well have it enforce the grid import limit too (by slightly reducing how aggressively it charges its batteries from the grid).

  1. It should be rare to have ‘too much’ solar generation like this once the charging algorithm for the house battery can be made to leave enough room for ‘tomorrow’s’ forecast solar generation ↩︎
  2. This should mean that any scheduled pre-conditioning ahead of a future journey won’t be affected, whereas that schedule gets wiped when Octopus control charge scheduling using the car API. It should also prevent the car charging for a few minutes whenever it’s plugged in. ↩︎
  3. There’s another 80 A fuse in the PowerWall Backup Gateway, which might blow first and is much easier to replace ↩︎

Outbuildings: Week 38, Day 5

Outbuildings: Week 38, Day 5

More tidying-up of the site and completing a few outstanding jobs inside but mostly finishing off the temporary, shallow ramp that provides access to the block-paved parking area. That needed two lorry-loads of recycled aggregate, on top of the larger-sized stone installed yesterday.

Recycled stone ‘ramp’ connecting the block-paved parking area by the Garages to the main driveway

This is ‘temporary’ in as much as nothing more permanent was included in the scope of the build contract. In due course some block paving will be brought further towards the House, but the extent of that paving and the choice of materials is part of the wider landscaping scheme for which the design is not yet confirmed. Overall it’s quite a large, flat area that could probably do with breaking up with some planting – perhaps in containers?

The digger, dumper and roller used for the drainage and driveway works have been off-hired and will be collected early next week.

This marks the end of the main work for the prime contractor but there’s still some subcontract work to complete:

  • The external staircase is getting a custom-made safety handrail which has been fabricated and galvanised and should be ready to install next week
  • The plumbing work needs another day or two of work to finish off, again expected next week
  • There’s about another day left to fully finish the vinyl flooring in the Utility Room and wet-room Shower Room

There are also a few items of work not included in the main build contract:

  • The wall needs tiling around the shower, before the shower fitting itself can be installed
  • The window sills need installing on the five square windows around the Courtyard, together with some adjustments to the doors and their seals
  • The alarm system needs some finishing touches, including installing the radio link to the House system and its monitoring station
  • The ventilation system needs commissioning (adjusting the fan speeds and vent openings) and the ‘external’ ducts need insulating
  • The kitchen units need installing in the Utility Room

It’s therefore close to the time when it’s appropriate to suspend these regular daily updates. For now, my thinking is to leave them running until the Architect declares ‘practical completion’ and Building Control are ready to issue their final certificate, which will probably be another week or two. I might delete the daily updates on days when there’s nothing to report.