A planned holiday day for the main build team today, but more progress from the electrical installation team.
A planned holiday day for the main build team today, but more progress from the electrical installation team.
Completion of the final section of roof tiling; the only element of the roof still left to finish is the installation of the Ridge tiles, which is still waiting for the delivery of suitable dry-fix ridge kits. Some were delivered on Tuesday but they weren’t the ones which had been ordered – and the ‘correct’ ones seem to be in short supply.
Work has now moved on to the installation of the guttering.