More progress on the roof tiling, completing the South-facing section of the Garage roof then moving back to progress the North-facing section – and good progress with the first-fix electrical installation (although there’s an element of second-fix happening too, since the usual requirement to wait for plastering and plasterboard installation etc. doesn’t apply to this non-domestic building).