Week 55, Day 5

Week 55, Day 5:

  • More tidying up of the site, most notably stacking the waste wood to make a bonfire for Bonfire Night
  • Some minor re-grinding of the polished concrete floor to remove a few scratches and even things up around one of the recessed floor boxes, followed by an overall re-sealing and re-buffing of all the polished concrete areas
  • A delivery of concrete blocks for the retaining wall
Week 55, Day 5

Week 55, Day 5

Bonfire from waste wood, old pallets etc.

Bonfire from waste wood, old pallets etc.

Week 31, Day 4

Week 31, Day 4:

  • If you look carefully you can see a change in the overview photo – the timber cladding is now installed along about half of the southern elevation
  • Buffing the polished concrete floor, once it had dried following yesterday’s wet grinding
  • Installing the plasterboard in the Communications Room (basically a cupboard off the Office on the second floor, over the balcony, where all the data cables run back to)
  • More electrical and plumbing first-fix
Week 31, Day 4

Week 31, Day 4

Polished concrete floor

Polished concrete floor in Open Plan area

Pink FireLine plasterboard in the Communications Room

Pink FireLine plasterboard in the Communications Room