Outbuildings: Week 31, Day 2

Outbuildings: Week 31, Day 2

The first five of the reconstituted stone steps delivered yesterday have been installed. (A further three slabs were delivered but those are destined for the top landing and can’t be installed yet.) The stone looks a bit yellow (more so than the Bath stone sample provided) but it should tone down soon enough. For some reason the slabs had been made too long – perhaps with some assumption about them being built-in to the wall (rather than supported on an additional skin of blockwork) – so needed cutting down on-site.

The first five of the stone steps installed for the External Staircase

The stone foundation for the parking area by the Garages was levelled and compacted. It has a shallow fall to the North (the left of the photo) to help with water run-off into the grass – although it will use permeable block paving so most of the water will percolate through the paving and into the crushed stone base layer – then on into the ground beneath.

Crushed stone foundation for the block paved parking area North of the Garage Doors

Also some more progress in the Courtyard, bringing some of the land drains together into an inspection chamber and planning the route to the next inspection chamber, which needs to avoid a foul drainage pipe and the water mains.

A little more plumbing too, mounting the four outside taps.

Outbuildings: Week 28, Day 1

Outbuildings: Week 28, Day 1

A very windy day all across the country, with gusts up to 50mph in Derby, which ruled out high-level work. There was a fair bit of rain over the weekend, leaving large puddles in the Courtyard (bearing in mind the downpipes are currently just dumping water onto the ground),

Good progress with installing the doors and windows in the Workshop and Utility Room. All 5 of the 910mm-square windows were fitted together with 2 of the 3 doors. That just leaves the first-floor door (at the top of the external staircase) and the bi-fold door between the Workshop and the Garage to be installed tomorrow. There’s a minor issue to be sorted out with the window sills.

Further progress with the electrical installation – mostly the lights in the Garages – and completion of the first of the buttresses (with a little work on the second buttress, before running out of ready-mixed mortar). Start of work on the plasterboard ceiling in the Utility Room.