Outbuildings: Week 39, Day 1

Outbuildings: Week 39, Day 1

Good progress on the plumbing today, with the pipework now completed in the Ground Floor Store Room which is the ‘hub’ for the plumbing installation – though it still needs insulating (especially since the store room will remain unheated). With this pipework completed, there is now mains water coming into the Outbuildings (via the blue MDPE pipe in the photo below) and harvested rainwater in both the Outbuildings and the House (coming in from the submersible pump in the underground tank via the flexible hose connection into the black and yellow pump controller, and going out to the House via the black and green MDPE pipe, running into the same duct as the blue pipe).

Mains and Rainwater pipework in the Ground Floor Store Room

The diagram pinned to the wall is a schematic I drew for the plumbers, showing how the components needed to be arranged – reproduced below.

Schematic for rainwater harvesting pipework

I’ll write more about the rainwater harvesting system in a separate technical article, since it’s a relatively unusual thing to incorporate in a domestic property and I’m pleased with how it’s all come together. The Wisy Multimat pump and controller (in the photo with a temporary plastic bag rather than the supplied cover) are impressively very well-engineered. While they weren’t cheap they seem good value. The pump and controller are both critical components of the rainwater supply system and it’s not at all easy to arrange for a mains water backup if one of them fails, due to the regulations about protecting mains water supplies from contamination from “Category 5” liquids (since rainwater is considered as ‘bad’ as raw sewage).

Outbuildings: Week 38, Day 4

Outbuildings: Week 38, Day 4

The main build team are firmly in ‘finishing up’ mode, having completed the drainage works yesterday. The rainwater attenuation pond is now completed and the area to the East of that has been re-levelled and profiled into the GrassGuard blocks bounding the block-paved parking area.

Completed rainwater attenuation pond, looking East towards the inlet

Next up was starting the ramped driveway approach connecting the block-paved parking area to the driveway by the House, forming a foundation layer with relatively large-sized stones on top of a heavy landscape fabric, consolidated with a mechanical roller.

The air-to-air heat pump has now been fully commissioned and is working to heat the Workshop and Utility Room to a ‘background’ level of 18C. Some of the plumbing team were back on-site hooking up the connections to the Workshop sink and installing some of the pipe insulation.