Almost all of today’s activity was off to the left of the overview photo, erecting the first set of roof trusses on the (relatively small) two-storey section and preparing to start installing the shallow brick arches over the garage door openings.

The steel beam over the wide internal door opening also got installed – visible on the photo above (and also in the overview shot).
In addition, there was one of the monthly Site Meetings with the Architect, which includes a valuation of progress to date (and materials delivered to site) to support the monthly stage-payment on the building works.