Week 43, Day 4:
- More oak flooring, this time on the first floor landing
- Installing the furniture for the WC and the washbasin in the Family Bathroom
- More external window reveals and sills
- More second-fix electrical
- More filling, sanding and painting around the recessed down-lights in the Open Plan area