Week 42, Day 3

Week 42, Day 3:

  • Some more work on the zinc roof though progress was restricted by the strong and gusty wind – not compatible with manipulating 4m x 0.5m lengths of zinc sheeting at height
  • Good progress on the cedar cladding for the reveals around the windows on the south side of the first floor, where the scaffolding will be removed in a couple of days
  • Applying the protective oil to the cedar cladding most recently installed – e.g. the window reveals and around the balcony
  • More second-fix plumbing, including the supply and waste connections for the kitchen sink and dishwasher – easier before the worktops are installed – and the twin washbasin the the Master Bedroom En-Suite
  • More second-fix electrical, mainly the isolators for the various kitchen appliances
  • More plastering, mainly in the Hallway
Week 42, Day 3

Week 42, Day 3

The start of the final section of the north roof, east of the rooflights

The start of the final section of the north roof, east of the rooflights

Window reveals and sills on the first floor, south side

Window reveals and sills on the first floor, south side

Doors installed on integrated fridge and freezer

Doors installed on integrated fridge and freezer

Plaster in the Hallway

Plaster in the Hallway

Twin washbasin in Master Bedroom En-Suite

Twin washbasin in Master Bedroom En-Suite