Week 42, Day 1

Week 42, Day 1:

  • The team from Full Metal Roofing were back on-site and completed about half of the zinc roof covering on the curved section of the north roof
  • More plastering, including the Hall ceiling and the Balcony ceiling
  • Trimming back the cedar cladding around the first- and second-floor windows ready for boards on the reveals and the window sills
  • Marking out the kitchen ceiling ready for the in-ceiling loudspeakers
  • (Actually on Saturday): Transporting the bespoke (extra-tall) interior doors from the builders’ workshop to site