Week 43, Day 3

Week 43, Day 3:

  • The main finishing touches on the zinc roofing, with just the down-pipes left to install
    • This included the installation of the two roof windows which have been on-site since mid-February
  • More work on the external window reveals and sills
  • More second-fix electrical, mostly sockets and switches on the first floor
  • More second-fix plumbing, mostly installing the “wet room” (i.e. recessed into the floor) shower tray in the ground-floor shower room
  • Mostly completing the installation of the engineered oak flooring in the Living Room, with just the circular in-lays in the floor box lids to complete
  • Filling and sanding the recessed plaster down-lights in the open plan area in preparation for painting the ceiling
  • Starting to commission the computer network and WiFi Access Points
Week 43, Day 3

Week 43, Day 3

Wider view from main camera location, showing completed zinc fascias

Wider view from main camera location, showing completed zinc fascias

Western elevation, showing completed zinc fascia

Western elevation, showing completed zinc fascia

Roof windows over Bedroom 5

Roof windows over Bedroom 5

Roof windows from the inside

Roof windows from the inside

Wet-room shower tray on ground floor

Wet-room shower tray on ground floor

Engineered oak flooring in Living Room

Engineered oak flooring in Living Room