Week 20, Day 1:
- After several days without significant rain the site is finally starting to dry out – but not for long since there’s rain forecast for the next few days
- More work on adding the extra insulation and boarding to the main roof
- The SIPS installers left some blue breathable membrane to use as a temporary cover to keep out the worst of the rain but didn’t install it because there was more work to do on the roof; it got installed today