Week 13, Day 2:
- Some limited preparation for installing the timber floor structure for the second floor, although little progress can be made until the detailed design for the transition between the masonry and the SIP construction is agreed.
Week 13, Day 2 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.