Week 58, Day 4

Week 58, Day 4:

  • More work on the retaining wall, preparing for back-filling
    • Installing the outside tap by the front steps, taking care with the pipe runs so this can be used to drain the water from all the outside pipework in winter
    • Installing the perforated pipe in a layer of pea gravel
    • Starting to back-fill the other sections with subsoil excavated previously
Week 58, Day 4

Week 58, Day 4

Perforated pipe installed in pea gravel behind retaining wall

Perforated pipe installed in pea gravel behind retaining wall