Week 74, Day 5

Week 74, Day 5:

  • A bit more progress on the stone cladding at the north-east corner
  • Another good day for solar electricity production – just over 38 kWh generated and a average of 5.318 kW between 11:15 and 11:30 (from an installation rated for 5.4 kW peak production)
    • I see shorter peaks higher than 5.4 kW – some close to 6.0 – but so far those have not been sustained for long, typically because of clouds which shade the panels
Week 74, Day 5

Week 74, Day 5

More progress on the stone cladding on the north-east corner

CC BY-SA 4.0 Week 74, Day 5 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.