Week 2, day 5:
- Delivery of a 20-tonne lorry load of stone chippings.
- This will be used to stop the area by the site cabins becoming so muddy in wet weather.
- 20 tonnes of stone chippings looks at lot smaller than you’d think!
- Completing the excavation of the second (southern) GSHP collector trench.
- Installing marker pegs in the foundation trenches to indicate the required depth of the foundation concrete.
- The overview photo shows the laser level used to ensure the pegs were all at the right height in relation to Finished Floor Level.