Week 3, Day 2:
- More deliveries:
- 2 x 20 tonne loads of sand to line the bottom of the GSHP collector trenches.
- A small tele-handler / fork-lift for unloading deliveries and moving materials around the site.
- The concrete blocks for the walls below floor level.
- The Ancon TeploTie wall ties.
- Starting work on the trenches that connect the main GSHP collector trenches to the house.