Week 3, Day 2

Week 3, Day 2:

  • More deliveries:
    • 2 x 20 tonne loads of sand to line the bottom of the GSHP collector trenches.
    • A small tele-handler / fork-lift for unloading deliveries and moving materials around the site.
    • The concrete blocks for the walls below floor level.
    • The Ancon TeploTie wall ties.
  • Starting work on the trenches that connect the main GSHP collector trenches to the house.
Week 3, Day 2

Week 3, Day 2

Marking out trenches for GSHP collector tails

Marked-out trenches for GSHP collector tails – green is centre line, red is electricity cable

Concrete block delivery

Concrete block delivery

Adding sand to line bottom of GSHP collector trench

Adding sand to line the bottom of the northern GSHP collector trench

CC BY-SA 4.0 Week 3, Day 2 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.