Week 7, Day 2

Week 7, Day 2:

  • Very good progress installing almost all of the concrete floor beams and roughly 40% of the dark grey 3.6N infill blocks. Stronger (7.3N) blocks are required in some areas, wherever a wall will be supported by the floor structure.