Week 17, Day 1

Week 17, Day 1:

  • Yet another wet day.
  • Anvil Hire delivered a digger ready for excavating the trenches for the service connections to the house (electricity and water) which was used to tidy up some of the rougher areas around the site.
  • Various other clearing and cleaning activities, given the weather. The beam and block floor got covered with a rough layer of mortar while the blocks were being laid which needs to be cleared off before laying the floor insulation, so some progress made with that.