Week 18, Day 3

Week 18, Day 3:

  • The rain arrived exactly as forecast
  • More good progress with the Structural Insulated Panel installation, despite the weather
  • The two roof windows were delivered
Week 18, Day 3

Week 18, Day 3

Unloading the second panel delivery of the day

Unloading the second panel delivery of the day

Positioning the first panel of the south roof

Positioning the first panel of the south roof

End-of-day view from the main camera location

End-of-day view from the main camera location

The crane, with boom retracted

The crane, with boom retracted

The crane is a Liebherr LTM 1040-2.1.

CC BY-SA 4.0 Week 18, Day 3 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.