Week 19, Day 5

Week 19, Day 5:

  • Starting to add the extra 100mm of thickness to the main roof, which was initially a cosmetic detail to make the roof overhangs look “right” but now includes an extra 100mm of insulation which helps to recover the margin for achieving Passivhaus certification
Week 19, Day 5

Week 19, Day 5

View from main camera location

Better view from main camera location

Extra boarding and insulation on north roof

Extra boarding and insulation on main roof

Better view of 100mm insulation

Better view of 100mm insulation

CC BY-SA 4.0 Week 19, Day 5 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.