  • Starting to round out the curved section of roof
  • The SIPS panels are planar and form a series of facets rather than a true curve
  • The finished curve is formed using 3 layers of 6mm plywood, glued together
Week 21, Day 2

Week 21, Day 2

Starting to install the first layer of 6mm plywood on the curved section of the roof

Starting to install the first layer of 6mm plywood on the curved section of the roof