Week 24, Day 2

Week 24, Day 2:

  • The team from Full Metal Roofing arrived as planned to start work on the zinc roof covering and set to work installing the concealed gutter near the bottom of the southern roof (just visible as a grey line on the first photo, with a close-up below)
  • Still more fine-tuning of the openings for the windows and external doors, in preparation for the installation team from ecoHaus Internorm who are due to start work on Thursday
Week 24, Day 2

Week 24, Day 2

Concealed gutter formed in zinc

Concealed gutter formed in zinc