Week 25, Day 3

Week 25, Day 3:

  • Preparation for the concrete floor slab, cleaning up the surface of the beam-and-block floor and laying a damp-proof membrane
  • Those strange white shapes on the left of the photo are piles of insulation boards to go between the beam-and-block ground floor structure and the overlying concrete floor slab, which will get polished in some areas, tiled in others and covered in oak flooring in the more formal rooms
Week 25, Day 3

Week 25, Day 3

View from main camera location with the windows and doors installed

View from main camera location with the windows and doors installed

CC BY-SA 4.0 Week 25, Day 3 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.