Week 54, Day 2:
- Installation of the Phone Line into the house, using the armoured cable previously routed from the Comms room to the underground joint box outside
- This isn’t operational yet due to a fault on the line between the Distribution Point and the Cabinet which should be fixed within a day or two
- Laying the rubber tiles over their underlay on the balcony
- These are Eurodec Premier Rubber Tiles in grey which protect the Sarnafil single-ply membrane beneath while allowing water to drain though