Week 63, Day 3

Week 63, Day 3:

  • Mostly landscaping today:
    • Removing the temporary drainage connection from the caravan to the sewage treatment plant (which was above ground in a small embankment)
    • Filling in the holes around the water mains stop-taps
    • Spreading another 20 tonnes of roadstone and filling the worst of the hollows (=puddles)
Week 63, Day 3

Week 63, Day 3

Levelled area to the north of the house, looking west

Levelled area to the north of the house, looking east

CC BY-SA 4.0 Week 63, Day 3 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.