Week 64, Day 5

Week 64, Day 5:

  • Some progress on the external door thresholds, preparing the bottom sections of the plywood boxes ready for the installation of the waterproofing membrane which will help to protect them (since they’re below DPC)
  • Quite a short build-day since the plan is to spend tomorrow (Saturday) sorting out the reasons for the air tightness falling short of the Passivhaus requirements and correcting the remaining problems so the next air test is successful
Week 64, Day 5

Week 64, Day 5

Waterproofing membrane on side door threshold

CC BY-SA 4.0 Week 64, Day 5 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.