Week 66, Day 1

Week 66, Day 1:

  • Removing the plasterboard under the balcony, at the western end of the Open Plan room, ready to close off the air leaks found on 21st January
    • Including various preparations to prevent dust escaping too far into the rest of the house
Week 66, Day 1

Week 66, Day 1

Plasterboard removed under balcony, ready for fixing the air leaks

CC BY-SA 4.0 Week 66, Day 1 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.