Week 68, Day 2

Week 68, Day 2:

  • More work on the door canopies, preparing to install the permanent waterproof membranes in place of the temporary polythene sheeting
  • Further progress on the preparations for the 14 low-level outside lights, which will be mounted on top of the stone cladding with their cables hidden within the cladding
Week 68, Day 2

Week 68, Day 2

Wiring for 1 of 14 outside wall lights (Nordlux Canto)

CC BY-SA 4.0 Week 68, Day 2 by Marsh Flatts Farm Self Build Diary is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.