Week 2, Day 3

Week 2, Day 3:

  • Digging the first trench for the Ground Source Heat Pump pipes, 1.5m wide x 50m long – not visible in the overview shot so see the second photo below
  • Site visit from MFA Building Control, to inspect the foundations before the concrete is poured (booked for Monday 2015-10-19)
  • Clearing the weeds and marking the location of the second GSHP trench ready for digging tomorrow
Week 2, Day 3

Week 2, Day 3

GSHP trench in-progress

Northern GSHP trench almost complete