Week 30, Day 3

Week 30, Day 3:

  • Delivery of the lighting fixtures required for first-fix, where they need to be incorporated into the plaster on the walls or ceilings
  • More electrical first-fix, including cabling the control points for the electric windows and blinds
  • More plumbing first-fix, including installing the pipework for the bath fillers and the digital shower control boxes
Week 30, Day 3

Week 30, Day 3

First-fix wiring for electric windows and blinds

First-fix wiring for electric windows and blinds

Mira Platinum digital shower mixers

Mira Platinum digital shower mixers