Week 30, Day 4

Week 30, Day 4:

  • More first-fixing
  • Plastering-in the air-tight tape on the southern bedroom walls, where these will get plasterboard rather than a wet plaster finish (which normally forms the air-tight layer)
  • More work on the studwork walls – especially on the second floor where the plasterboard will get installed first
Week 30, Day 4

Week 30, Day 4

Air-tight tape now plastered into place in master bedroom

Air-tight tape now plastered into place in master bedroom

Studwork wall in second floor bathroom

Studwork wall in second floor bathroom